Corrective Action Register Template
One register for every finding that needs fixing, whatever raised it: an inspection, an incident, a near miss, an observation or an audit. Each row has an owner, a due date and the evidence that closed it.
Kept per site or per area, updated as findings are raised, and reviewed at the weekly safety meeting until every open row is closed.
What is in the template
Register
Columns: Ref · Date raised · Source · Finding · Root cause · Corrective action · Owner · Due · Closed (date, evidence, verified by) · 14 rows per page
Source is the record that raised it: inspection, incident, near miss, observation or audit, with its number. A row closes only when the evidence is attached and someone other than the owner has verified it.
Overdue at this review
- Open rows
- Overdue rows
- Oldest open ref and date
- Escalated to
- Signature of reviewer
How to fill it in
- 1Give every finding a reference number and record where it came from, so the inspection or incident record and the action can always be matched.
- 2Write the finding as what was seen, then the root cause as why it happened. "Guard missing" is a finding; "guard removed for cleaning with no procedure to refit it" is a cause.
- 3Name one owner and one due date. An action with two owners has none.
- 4Close the row only with evidence (a photo, a document, a test record) and a second person verifying the fix.
- 5Count the overdue rows at every review and escalate the oldest.
A general template, not legal advice. Check it against the Act, the regulations and the codes of practice that apply to your site, and against your own safety management system. The MHSA section 11 requires an employer to identify hazards, assess risks and record the measures taken; the OHS Act section 8(2)(d) and (e) require the employer to establish what hazards exist and take the steps that remove or mitigate them. ISO 45001 clause 10.2 requires nonconformities and corrective actions to be recorded, with their effectiveness reviewed.
Convert this template into a digital form
Run it on an Android phone with no signal, attach photos as evidence, and every failed item raises an issue with an owner and a due date.
The same record in Inspecable
On paper the register is only as current as the last person who updated it. In Inspecable the same record keeps going:
- A failed inspection item raises a tracked issue with a due date on the spot, offline on Android; a manager assigns the owner.
- One corrective-action register is fed from inspections, incidents, near misses, observations and audits. Closure is refused without a method, evidence and a signature; the database enforces it.
- The closer cannot be the assignee, a signed effectiveness review follows, and overdue items move up the chain under escalation rules you set.
Questions
What is the difference between a corrective action and a preventive action?
A corrective action fixes the cause of something that has already gone wrong: a failed check, an incident, an audit finding. A preventive action addresses a hazard before it causes harm. ISO 45001 folds both into clause 10.2 and the risk process; one register with a source column handles both.
Who should own a corrective action?
The person who can actually get it done in the area: a supervisor, an engineer, a contractor manager. Not the SHEQ officer who raised it, and not a department. One name per row, and someone other than the owner verifies the closure.
More free templates
- Legal Register Template South Africa (OHS Act and MHSA)
- Legal Appointments Template: 16.2 Appointment Letter and Appointments Register
- Toolbox Talk Topics and Toolbox Talk Record Template (with Attendance Register)
- Safety File Checklist and Index Template (Construction Regulations)
- Risk Assessment Template South Africa: Baseline Risk Assessment (HIRA)
- Permit to Work Template (with Isolation Register)
- Incident and Near-Miss Investigation Report Template (OHS Act and MHSA)
- ISO 45001 Internal Audit Checklist Template
- Monthly Safety Report Template (SHEQ)
- Asset Register Template (Excel-Import Ready)
- Fitness for Duty Declaration and Register
- Contractor Compliance Register Template (Section 37 Mandataries)
- Business Case Template for Inspection and Compliance Software
- Planned Task Observation (PTO) Form and Register
- Job Safety Analysis (JSA) Template
- Lockout Tagout (LOTO) Isolation Checklist and Lock Register
- Hot Work Permit Template (Welding, Cutting and Grinding)
- Scaffold Inspection Checklist, Register and Handover Certificate
- API 570 Piping Inspection Record: Thickness, Corrosion Rate and Remaining Life
- ISO 9001:2026 Internal Audit Checklist and Transition Checklist
- OHSAS 18001 to ISO 45001 Migration and Gap Checklist
Looking for an inspection checklist instead? Free checklists.